8:01am- Removing water in order to build a working pad for bent 3
10:23am- Placing dirt on top of 66” RCP and Continue to excavate the West approach
11:26am- Water pumped, forms built waiting on concrete for work pad
12:52pm- Poured concrete for a working pad at bent 3
1:44pm- Continue to excavate at the West approach