3414 Polk Co Bridge
Wednesday, January 31, 2018
Pour cap at #4 bent 1 31 2018
1:45pm- Start pouring concrete for bent 4 cap. Late due to broken boiler.
2:21pm- Finished product after the pour at bent 4 for the cap.
3:27pm- Finish the day with assembling rebar cage located at bent 1.
Tuesday, January 30, 2018
Pour caps 1 30 2018
10:04am- Moving material to build the wall for abutment #1
10:59am- Forming the wall at the west abutment
1:16pm- Pouring concrete for the intermediate bent 3 cap.
2:25pm- Continue to form wall for West abutment
2:55pm- Pouring cap for intermediate bent 2
3:37pm- Finished day with forming more of the West abutment wall
Monday, January 29, 2018
Frame bent 4 1 29 2018
8:55am- Finish framing intermediate bents
10:42am- Continue to frame intermediate Bents
10:52am- Setting rebar frame for end bent 4
11:24am- Start framing the # 4 endbent
1:08pm- Continue to form and build rebar cage for bent 4
2:48pm- Continue to form and build rebar cage for bent 4
3:35pm- Finish with forms and building cap for bent 4
Thursday, January 25, 2018
Build working pads 1 25 2018
8:12am- Framing for work pad at bent 1
10:02am- Framing caps for intermediate bents 2-3
11:03am- Continue to frame for intermediate bents 2-3
12:18pm- Framing for bent 4 working pad
12:56pm- Building rebar cage assembly for end bent 1
1:37pm- Pouring work pads for end Bents 1-4
Wednesday, January 24, 2018
Intermediate cap build 1 24 2018
9:24am- Building rebar steel frame for the intermediate bent cap
10:18am- Cutting I Beam’s to length for intermediate bent caps.
11:10am- Rebar cage for intermediate bent 3 cap set in place.