10:51am- Remove Wall forms from around bent 1
11:28am- Applying dirt around cap for bent 4 after flooding removed dirt.
12:41pm- Finished product at the #4 bent
12:47pm- Digging 4’ toe for rock blanket at the East approach
1:32pm- Building rock blanket for bent 4 East approach
2:30pm- Building retaining wall located at the West approach
4:13pm- Finishing half of the rock blanket and toe in front of the East approach