3414 Polk Co Bridge
Tuesday, March 13, 2018
Strip retaining wall 3 12 18
11:15am- Setting up for I girder delivery tomorrow.
2:12pm- Removing forms from West approach
2:30pm Continue to remove forms from the West approach retaining wall
Thursday, March 8, 2018
Retaining wall concrete pour 3 8 18
Wednesday, March 7, 2018
Finish forming retaining wall 3 7 18
10:54am- Continue to place forms and bracing for the retaining wall
11:42am- Final product prior to pouring concrete tomorrow
Form retaining wall 3 6 18
12:00pm- Setting forms for the retaining wall at the West approach
12:30pm- Finished placing riprap at the stream face of bent 1
1:19pm- Continue to form for the retaining wall
Monday, March 5, 2018
Tie rebar for retaining wall 3 5 18
9:56am- Finished product from Friday’s pour of the footing for retaining wall
10:04am- Tieing rebar together for the retaining wall
10:53am- Placing riprap at the creek face of bent 1
1:39pm- Continue to place riprap at the stream face of bent 1
2:19pm- Finished tying rebar start setting forms for retaining wall
Friday, March 2, 2018
Pour retaining wall footing 3 2 18
10:57-Start pouring footings for retaining wall
12:35pm- Continue to pour concrete for the retaining wall footing
1:11pm- Close to finishing footing for retaining wall at the West approach
Thursday, March 1, 2018
Retaining wall at West approach 3 1 18
8:43am- Continue to build retaining wall at the West approach placing rebar with wire ties.
9:33am- Continue to place riprap in front of bent 4 stream face
11:25am- Continue to attach rebar together for the retaining wall footing
1:00pm- Finishing touches on rebar for the retaining wall footings