Continue with decking 3 21 18


9:22am- Sealing bent caps
9:54am- Continue with I girder jacks and setting plywood 






11:07am- Forming for the diaphragm at bent 1
1:06pm- Finishing up with I girder jacks


1:07pm- Tying rebar for the intermediate Bents
2:09- Continue to form the stream side of bent 1 diaphragm 
3:27pm- Finished with the Deck overhang










Continue to set girder jacks 3 20 18


9:45am- Continue to set I girder jacks
10:02am- Forming for diaphragm at bent 3



10:25am- Continue to set jacks on the side of I girders
10:49am- Breaking rock to build ramp in order to access bent 1
11:00am- Continue to form diaphragm at bent 3
1:50pm- Building an approach ramp for bent 1
2:21pm- Continue to form for bent 3
3:30pm- Breaking rock and moving dirt for the access road at the West approach
4:01pm- Setting sheets of plywood on top of I girder jacks















Thursday, March 15, 2018

Wednesday, March 14, 2018

Setting deck panels 3 14 18


11:14am- Setting Deck panels



1:17pm- Adjusting deck panel heights









Tuesday, March 13, 2018

Setting I girders 3 13 18


11:06am- First truck arrives to start setting girders in between Bents 2/3.


11:39am- Continue to set girders in between bent 2 and 3.
11:58am- Finish setting girders for the intermediate Bents.




2:15pm- Set girders from West abutment to intermediate bent 2


2:39pm- Setting last girder at the West approach.


3:16pm- Setting girders at the East approach 







4:17pm- Final product after the day