Thursday, March 22, 2018

Deck prepping tying steel 3 22 18


10:32am- Tying steel at the intermediate and end Bents





11:23am- Tying steel for the girder overhangs


1:16pm- Excavating rock and dirt at the West approach.


1:30pm- Finished tying steel for the day
2:18pm- Continue to break rock and excavate dirt at the West approach







Wednesday, March 21, 2018

Continue with decking 3 21 18


9:22am- Sealing bent caps
9:54am- Continue with I girder jacks and setting plywood 






11:07am- Forming for the diaphragm at bent 1
1:06pm- Finishing up with I girder jacks


1:07pm- Tying rebar for the intermediate Bents
2:09- Continue to form the stream side of bent 1 diaphragm 
3:27pm- Finished with the Deck overhang










Continue to set girder jacks 3 20 18


9:45am- Continue to set I girder jacks
10:02am- Forming for diaphragm at bent 3



10:25am- Continue to set jacks on the side of I girders
10:49am- Breaking rock to build ramp in order to access bent 1
11:00am- Continue to form diaphragm at bent 3
1:50pm- Building an approach ramp for bent 1
2:21pm- Continue to form for bent 3
3:30pm- Breaking rock and moving dirt for the access road at the West approach
4:01pm- Setting sheets of plywood on top of I girder jacks















Thursday, March 15, 2018

Wednesday, March 14, 2018

Setting deck panels 3 14 18


11:14am- Setting Deck panels



1:17pm- Adjusting deck panel heights