Tuesday, April 3, 2018

Site visit inspection


10:00 am Crew is still working on deck

Crew is tying corral rail steel



Crew taking crane apart





Site visit inspection


Water is still over temporarily roadway 

Crew of seven tying deck steel


Monday, March 26, 2018

Continue tying steel on deck 3 26 18


9:07am- Setting rebar on the deck surface.


10:07am- Continue to set rebar on the surface of the deck

Thursday, March 22, 2018

Deck prepping tying steel 3 22 18


10:32am- Tying steel at the intermediate and end Bents





11:23am- Tying steel for the girder overhangs


1:16pm- Excavating rock and dirt at the West approach.


1:30pm- Finished tying steel for the day
2:18pm- Continue to break rock and excavate dirt at the West approach







Wednesday, March 21, 2018

Continue with decking 3 21 18


9:22am- Sealing bent caps
9:54am- Continue with I girder jacks and setting plywood 






11:07am- Forming for the diaphragm at bent 1
1:06pm- Finishing up with I girder jacks


1:07pm- Tying rebar for the intermediate Bents
2:09- Continue to form the stream side of bent 1 diaphragm 
3:27pm- Finished with the Deck overhang










Continue to set girder jacks 3 20 18


9:45am- Continue to set I girder jacks
10:02am- Forming for diaphragm at bent 3



10:25am- Continue to set jacks on the side of I girders
10:49am- Breaking rock to build ramp in order to access bent 1
11:00am- Continue to form diaphragm at bent 3
1:50pm- Building an approach ramp for bent 1
2:21pm- Continue to form for bent 3
3:30pm- Breaking rock and moving dirt for the access road at the West approach
4:01pm- Setting sheets of plywood on top of I girder jacks