Monday, April 9, 2018

Setting concrete deck machine 4 9 18


9:07am- Getting ready to set the deck machine in place

9:20- Setting Deck marching on top of form walls
10:05am- Touching up on loose ends with forms


10:19am- Setting rail height for concrete machine
12:21pm- Cleaning the deck, prepping for concrete pour

Thursday, April 5, 2018

Continue with deck steel 4 5 18


11:54am- Placing steel for corral rails
12:44pm- Continue to build abutment diaphragm located at the East approach.
12:51pm- Working on steel at the West approach



1:40pm- Continue to tie steel at the East approach


Wednesday, April 4, 2018

Assembling deck steel 4 4 18


10:41pm- Tying deck steel
12:55pm- Continue to tie rebar on the bridge deck
1:44pm- Building forms for the bent 1 diaphragm
2:59pm- Building forms for the bent 4 diaphragm 

Tuesday, April 3, 2018

Site visit inspection


10:00 am Crew is still working on deck

Crew is tying corral rail steel



Crew taking crane apart





Site visit inspection


Water is still over temporarily roadway 

Crew of seven tying deck steel


Monday, March 26, 2018

Continue tying steel on deck 3 26 18


9:07am- Setting rebar on the deck surface.


10:07am- Continue to set rebar on the surface of the deck

Thursday, March 22, 2018

Deck prepping tying steel 3 22 18


10:32am- Tying steel at the intermediate and end Bents





11:23am- Tying steel for the girder overhangs


1:16pm- Excavating rock and dirt at the West approach.


1:30pm- Finished tying steel for the day
2:18pm- Continue to break rock and excavate dirt at the West approach