3414 Polk Co Bridge
Tuesday, April 24, 2018
Continue corral wall 4 24 18
8:50am- Breaking rock for the West approach
8:56am- Continue with corral wall forming
10:32am- Importing more dirt for the West approach
12:38pm- Continue to import dirt and compact
1:43pm- Finishing the SouthWest corner of the corral wall
Monday, April 23, 2018
Corral wall 4-23-18
9:30am- Forming around rebar for the corral wall
9:48am- Rip rap placed against retaining wall, imported dirt to the West approach and compacted.
11:41am- Forming corral wall
12:47pm- Continue to form corral wall
1:49pm- Forming corral wall on the south side of bridge
Wednesday, April 11, 2018
Deck pour 4 11 18
8:33am- Getting ready for today’s pour
9:17am- Deck pour begins at the East approach
9:41am- Continue with deck pour, heading West
10:44am- Finishing and tynin deck surface
11:28am- Importing dirt to the West approach and compacting
11:48am Continue to pour for the deck. Heading towards the West approach
1:54pm- Finished product and placing burlap on the decks surface
2:03pm- Continue to import dirt for the West approach
Tuesday, April 10, 2018
Prepping for deck pour 4 10 18
9:25am- Checking angle on the deck machine
10:20am- Continue to check depth and angle of machine
11:36am- Cutting more materials for tomorrow’s pour