Setting I girders 3 13 18


11:06am- First truck arrives to start setting girders in between Bents 2/3.


11:39am- Continue to set girders in between bent 2 and 3.
11:58am- Finish setting girders for the intermediate Bents.




2:15pm- Set girders from West abutment to intermediate bent 2


2:39pm- Setting last girder at the West approach.


3:16pm- Setting girders at the East approach 







4:17pm- Final product after the day





Strip retaining wall 3 12 18


11:15am- Setting up for I girder delivery tomorrow.
2:12pm- Removing forms from West approach
2:30pm Continue to remove forms from the West approach retaining wall



Wednesday, March 7, 2018

Finish forming retaining wall 3 7 18


10:54am- Continue to place forms and bracing for the retaining wall


11:42am- Final product prior to pouring concrete tomorrow





Form retaining wall 3 6 18


12:00pm- Setting forms for the retaining wall at the West approach


12:30pm- Finished placing riprap at the stream face of bent 1
1:19pm- Continue to form for the retaining wall





Monday, March 5, 2018

Tie rebar for retaining wall 3 5 18


9:56am- Finished product from Friday’s pour of the footing for retaining wall
10:04am- Tieing rebar together for the retaining wall


10:53am- Placing riprap at the creek face of  bent 1


1:39pm- Continue to place riprap at the stream face of bent 1




2:19pm- Finished tying rebar start setting forms for retaining wall



Friday, March 2, 2018

Pour retaining wall footing 3 2 18


10:57-Start pouring footings for retaining wall







12:35pm- Continue to pour concrete for the retaining wall footing





1:11pm- Close to finishing footing for retaining wall at the West approach