Wednesday, April 11, 2018

Deck pour 4 11 18


8:33am- Getting ready for today’s pour


9:17am- Deck pour begins at the East approach


9:41am- Continue with deck pour, heading West


10:44am- Finishing and tynin deck surface





11:28am- Importing dirt to the West approach and compacting


11:48am Continue to pour for the deck. Heading towards the West approach




1:54pm- Finished product and placing burlap on the decks surface






2:03pm- Continue to import dirt for the West approach






Tuesday, April 10, 2018

Prepping for deck pour 4 10 18


9:25am- Checking angle on the deck machine
10:20am- Continue to check depth and angle of machine

11:36am- Cutting more materials for tomorrow’s pour 



Monday, April 9, 2018

Setting concrete deck machine 4 9 18


9:07am- Getting ready to set the deck machine in place

9:20- Setting Deck marching on top of form walls
10:05am- Touching up on loose ends with forms


10:19am- Setting rail height for concrete machine
12:21pm- Cleaning the deck, prepping for concrete pour

Thursday, April 5, 2018

Continue with deck steel 4 5 18


11:54am- Placing steel for corral rails
12:44pm- Continue to build abutment diaphragm located at the East approach.
12:51pm- Working on steel at the West approach



1:40pm- Continue to tie steel at the East approach


Wednesday, April 4, 2018

Assembling deck steel 4 4 18


10:41pm- Tying deck steel
12:55pm- Continue to tie rebar on the bridge deck
1:44pm- Building forms for the bent 1 diaphragm
2:59pm- Building forms for the bent 4 diaphragm 

Tuesday, April 3, 2018

Site visit inspection


10:00 am Crew is still working on deck

Crew is tying corral rail steel



Crew taking crane apart