8:08am- Driving pile at bent 4
8:47am- Continue to drive pile at bent 4
9:31am- Finish driving pile at bent 4
11:20am- Placed silt fencing around imported dirt at the East approach.
12:11pm- Concrete arrived on site for bent 3 wall
12:49pm- Continue to pump concrete into bent 3 wall
3:08pm- Start driving pile into the ground at end bent 1
3:48pm- Continue to drive pile at end bent 1