3414 Polk Co Bridge

Showing posts with label 2-13-2018. Show all posts
Showing posts with label 2-13-2018. Show all posts

Tuesday, February 13, 2018

Site visit, continued forming on Bent 1 Wall


8:10 crew continued forming on Bent 1 Wall

2:20 crew putting the final touches to the forms for bent 1 Wall. Will pour tomorrow at noon 





3:20 crew started stripping forms on Bent 2 Cap 





Posted by James Sutton at 6:19 AM No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Labels: 2-13-2018
Older Posts Home
Subscribe to: Posts (Atom)

Contributors

  • Great River
  • James Sutton
  • Lee

Blog Archive

  • ▼  2018 (58)
    • ▼  May (10)
      • Guard Rail 5 17 18
      • Guard rail 5 16 18
      • Riprap 5 15 18
      • Approach slabs 5 14 18
      • Riprap and slab approach 5 10 18
      • riprap 5 9 18
      • Bridge clean up 5 8 18
      • Site visit, roadway compaction
      • North side corral wall 5 2 18
      • South Corral wall 5 1 18
    • ►  April (11)
    • ►  March (15)
    • ►  February (8)
    • ►  January (14)
  • ►  2017 (16)
    • ►  December (15)
    • ►  November (1)
Simple theme. Powered by Blogger.