7:11am- Approach Slabs are formed and rebar set. Rock pads have been set in front of 66” pipe and all of the fence post holes have been drilled at the South West approach.
7:18am- Continue to place riprap
8:04am- Rebar set and ready to pour concrete
10:49am- East approach completed
3:16pm- Start concrete pour for the West approach