Tuesday, January 30, 2018

Pour caps 1 30 2018


10:04am- Moving material to build the wall for abutment #1

10:59am- Forming the wall at the west abutment

1:16pm- Pouring concrete for the intermediate bent 3 cap.



2:25pm- Continue to form wall for West abutment



2:55pm- Pouring cap for intermediate bent 2

3:37pm- Finished day with forming more of the West abutment wall

Monday, January 29, 2018

Frame bent 4 1 29 2018


8:55am- Finish framing intermediate bents

10:42am- Continue to frame intermediate Bents

10:52am- Setting rebar frame for end bent 4




11:24am- Start framing the # 4 endbent



1:08pm- Continue to form and build rebar cage for bent 4



2:48pm- Continue to form and build rebar cage for bent 4



3:35pm- Finish with forms and building cap for bent 4




Thursday, January 25, 2018

Build working pads 1 25 2018


8:12am- Framing for work pad at bent 1

10:02am- Framing caps for intermediate bents 2-3


11:03am- Continue to frame for intermediate bents 2-3




12:18pm- Framing for bent 4 working pad
12:56pm- Building rebar cage assembly for end bent 1

1:37pm- Pouring work pads for end Bents 1-4




Wednesday, January 24, 2018

Intermediate cap build 1 24 2018


9:24am- Building rebar steel frame for the intermediate bent cap



10:18am- Cutting I Beam’s to length for intermediate bent caps.


11:10am- Rebar cage for intermediate bent 3 cap set in place.


Tuesday, January 23, 2018

Forms intermediate bent 1 23 2018


9:03am- Setting supports for the intermediate Caps

10:08am- Continue to build supports for the intermediate bent Caps

10:53am- Continue to install forms for the intermediate caps.



3:02pm- Installing wood on top of forms for Caps




Monday, January 22, 2018

Jobsite clean up 1 22 2018


1:17pm- Disassembling wall forms

2:27pm- Loading wall forms onto trailer for transportation.

3:57pm- Continue to load forms onto trailer for transportation.