Wednesday, January 31, 2018

Pour cap at #4 bent 1 31 2018


1:45pm- Start pouring concrete for bent 4 cap. Late due to broken boiler.




2:21pm- Finished product after the pour at bent 4 for the cap.

3:27pm- Finish the day with assembling rebar cage located at bent 1.


Tuesday, January 30, 2018

Pour caps 1 30 2018


10:04am- Moving material to build the wall for abutment #1

10:59am- Forming the wall at the west abutment

1:16pm- Pouring concrete for the intermediate bent 3 cap.



2:25pm- Continue to form wall for West abutment



2:55pm- Pouring cap for intermediate bent 2

3:37pm- Finished day with forming more of the West abutment wall

Monday, January 29, 2018

Frame bent 4 1 29 2018


8:55am- Finish framing intermediate bents

10:42am- Continue to frame intermediate Bents

10:52am- Setting rebar frame for end bent 4




11:24am- Start framing the # 4 endbent



1:08pm- Continue to form and build rebar cage for bent 4



2:48pm- Continue to form and build rebar cage for bent 4



3:35pm- Finish with forms and building cap for bent 4




Thursday, January 25, 2018

Build working pads 1 25 2018


8:12am- Framing for work pad at bent 1

10:02am- Framing caps for intermediate bents 2-3


11:03am- Continue to frame for intermediate bents 2-3




12:18pm- Framing for bent 4 working pad
12:56pm- Building rebar cage assembly for end bent 1

1:37pm- Pouring work pads for end Bents 1-4




Wednesday, January 24, 2018

Intermediate cap build 1 24 2018


9:24am- Building rebar steel frame for the intermediate bent cap



10:18am- Cutting I Beam’s to length for intermediate bent caps.


11:10am- Rebar cage for intermediate bent 3 cap set in place.