Tuesday, January 23, 2018

Forms intermediate bent 1 23 2018


9:03am- Setting supports for the intermediate Caps

10:08am- Continue to build supports for the intermediate bent Caps

10:53am- Continue to install forms for the intermediate caps.



3:02pm- Installing wood on top of forms for Caps




Monday, January 22, 2018

Jobsite clean up 1 22 2018


1:17pm- Disassembling wall forms

2:27pm- Loading wall forms onto trailer for transportation.

3:57pm- Continue to load forms onto trailer for transportation.


Thursday, January 11, 2018

End bent 1 pile driving 1 11 2018


7:55am- Finish driving pile at end bent 1

8:21am- Wrapping intermediate bent 3 in preparation for the cooler weather

11:28am- Final product after wrapping intermediate bent 3 with insulated blankets.

11:45am- Finished product after all pile are set at end bent 1



12:00pm- Silt fencing placed at the West approach.


Wednesday, January 10, 2018

Driving pile at end bent 4 1 10 2018


8:08am- Driving pile at bent 4


8:47am- Continue to drive pile at bent 4



9:31am- Finish driving pile at bent 4

11:20am- Placed silt fencing around imported dirt at the East approach.





12:11pm- Concrete arrived on site for bent 3 wall

12:49pm- Continue to pump concrete into bent 3 wall

3:08pm- Start driving pile into the ground at end bent 1


3:48pm- Continue to drive pile at end bent 1

Tuesday, January 9, 2018

Forming wall at bent 3. 1 9 2018


9:40am- Prepping dirt pad to drive pile at bent 4



10:53am- Continue to finish forming for the wall at bent 3

11:11am- Checking for accurate distance between bent 3 and bent 4.



1:03pm- Prepping pad at bent 4 for pile driving

2:02pm- Prepping the pad at bent 1 for pile driving

4:04pm- Templet set up at the intermediate bent 3 for pile driving

4:13pm- Driving first pile at bent 3

Monday, January 8, 2018

Attach steel for bent 3. 1 8 2018


9:36am- Setting steel at intermediate bent 3



10:52am- Continue to tie steel at the intermediate bent 3.

12:09pm- Finish tying steel at bent 3 prepping for forms.
 
1:12pm- Both walls installed at bent 3


2:42pm- Attaching bracing to secure both walls at bent 3.

3:50pm- Continue to secure both walls at bent 3 for Wednesday’s concrete pour.