3414 Polk Co Bridge
Tuesday, February 13, 2018
Site visit, continued forming on Bent 1 Wall
8:10 crew continued forming on Bent 1 Wall
2:20 crew putting the final touches to the forms for bent 1 Wall. Will pour tomorrow at noon
3:20 crew started stripping forms on Bent 2 Cap
Monday, February 12, 2018
Site visit, working on Bent 1 Wall
9:35 crew started taking forms off bent 4 Cap, crane operator and foreman working on crane. A hose has a hole and will have to get a new one
10:30 crew started working on Bent 1 Wall, foreman came back with hoses but was the wrong fittings.
1:15 More forms going up.
1:40 more forms
2:30 crew still forming up wall for bent 1
3:10 another form in place.
Thursday, February 1, 2018
Rebar for end bent 1 Wall 2 1 2018
11:40am- Build rebar Cage for end bent 1
11:41am- Continue to build rebar cage and forms for bent 1
2:44pm- Finish the day with assembling more rebar at bent 1
Wednesday, January 31, 2018
Pour cap at #4 bent 1 31 2018
1:45pm- Start pouring concrete for bent 4 cap. Late due to broken boiler.
2:21pm- Finished product after the pour at bent 4 for the cap.
3:27pm- Finish the day with assembling rebar cage located at bent 1.
Tuesday, January 30, 2018
Pour caps 1 30 2018
10:04am- Moving material to build the wall for abutment #1
10:59am- Forming the wall at the west abutment
1:16pm- Pouring concrete for the intermediate bent 3 cap.
2:25pm- Continue to form wall for West abutment
2:55pm- Pouring cap for intermediate bent 2
3:37pm- Finished day with forming more of the West abutment wall
Monday, January 29, 2018
Frame bent 4 1 29 2018
8:55am- Finish framing intermediate bents
10:42am- Continue to frame intermediate Bents
10:52am- Setting rebar frame for end bent 4
11:24am- Start framing the # 4 endbent
1:08pm- Continue to form and build rebar cage for bent 4
2:48pm- Continue to form and build rebar cage for bent 4
3:35pm- Finish with forms and building cap for bent 4