Tuesday, December 26, 2017

Excavation at East app 12 26 2017


9:44am- Excavating old bridge at the West approach.

10:57am- Excavating at the East approach.

12:43pm- Excavating at the East approach

4:13pm- Excavating for clean dirt

Thursday, December 21, 2017

Excavating West approach 12 21 22


8:01am- Removing water in order to build a working pad for bent 3

10:23am- Placing dirt on top of  66” RCP and Continue to excavate the West approach 



11:26am- Water pumped, forms built waiting on concrete for work pad

12:52pm- Poured concrete for a working pad at bent 3





1:44pm- Continue to excavate at the West approach



Wednesday, December 20, 2017

Excavating for bent 3 12 20 17


9:29am- Setting more 66” storm water pipe at the West approach.




10:43am- Excavating for bent 3

11:14am- Continue to install storm drain pipe at the West approach



1:42pm- Finished placing RCP culvert with FES at the West approach.

2:36pm- Installing structural steel piles at bent 3


3:12pm- Structual steel piles all set at bent 3

Tuesday, December 19, 2017

Pre bore bent 3 -12 19 17


9:33am- Excavating at the West approach for the 66” RCP culvert

10:15am- Pre boring the first set of holes for bent 3



12:41pm- Grading for the storm water pipe installation. 

1:24pm- Continue to pre bore at bent 3

Monday, December 18, 2017

Site visit, Poured Bent 2 Wall

 Contractor was making final adjustment to the forms on Bent 2 wall

 Checked rebar and form work, all checked good.


 Contractor has started installing the 66" RCP




 Started pouring Concrete at 1:18, I tested concrete: Slump 41/2", Air 3.5/5. Air was low on all trucks. Had to check all truck, overall pour went good.



Thursday, December 14, 2017

Continue to build bent 2 12 14 17


9:30am- Material was dropped off for new water pipe

10:17am- Continue to form the intermediate bent 2



11:26am- Apply side to the forms for bent 2

12:34pm- More storm drain product dropped off. 

1:17pm- Burning brush pile from clearing and grubbing.