3414 Polk Co Bridge
Thursday, January 25, 2018
Build working pads 1 25 2018
8:12am- Framing for work pad at bent 1
10:02am- Framing caps for intermediate bents 2-3
11:03am- Continue to frame for intermediate bents 2-3
12:18pm- Framing for bent 4 working pad
12:56pm- Building rebar cage assembly for end bent 1
1:37pm- Pouring work pads for end Bents 1-4
Wednesday, January 24, 2018
Intermediate cap build 1 24 2018
9:24am- Building rebar steel frame for the intermediate bent cap
10:18am- Cutting I Beam’s to length for intermediate bent caps.
11:10am- Rebar cage for intermediate bent 3 cap set in place.
Tuesday, January 23, 2018
Forms intermediate bent 1 23 2018
9:03am- Setting supports for the intermediate Caps
10:08am- Continue to build supports for the intermediate bent Caps
10:53am- Continue to install forms for the intermediate caps.
3:02pm- Installing wood on top of forms for Caps
Monday, January 22, 2018
Jobsite clean up 1 22 2018
1:17pm- Disassembling wall forms
2:27pm- Loading wall forms onto trailer for transportation.
3:57pm- Continue to load forms onto trailer for transportation.
Thursday, January 11, 2018
End bent 1 pile driving 1 11 2018
7:55am- Finish driving pile at end bent 1
8:21am- Wrapping intermediate bent 3 in preparation for the cooler weather
11:28am- Final product after wrapping intermediate bent 3 with insulated blankets.
11:45am- Finished product after all pile are set at end bent 1
12:00pm- Silt fencing placed at the West approach.
Wednesday, January 10, 2018
Driving pile at end bent 4 1 10 2018
8:08am- Driving pile at bent 4
8:47am- Continue to drive pile at bent 4
9:31am- Finish driving pile at bent 4
11:20am- Placed silt fencing around imported dirt at the East approach.
12:11pm- Concrete arrived on site for bent 3 wall
12:49pm- Continue to pump concrete into bent 3 wall
3:08pm- Start driving pile into the ground at end bent 1
3:48pm- Continue to drive pile at end bent 1