Tuesday, February 27, 2018

Site visit rebuild East approach 2 27 2018


10:51am- Remove Wall forms from around bent 1

11:28am- Applying dirt around cap for bent 4 after flooding removed dirt.



12:41pm- Finished product at the #4 bent


12:47pm- Digging 4’ toe for rock blanket at the East approach

1:32pm- Building rock blanket for bent 4 East approach



2:30pm- Building retaining wall located at the West approach





4:13pm- Finishing half of the rock blanket and toe in front of the East approach

Monday, February 26, 2018

Site visit flood damage 2 26 2018


9:33am- Cleaning residual debris from around intermediate bent 3

9:54am- Cleaning debris from around end bent 4





10:28am- East approach eroded away by swift water.







11:27am- Continue to remove debris from underneath bent 4





12:48pm- Road signs carried away by swift water

Tuesday, February 20, 2018

Thursday, February 15, 2018

Wednesday, February 14, 2018

Site visit, pour Bent 1 Wall


11:00 pump truck arrived

Forms and steel all looked good





Concrete arrived and I tested it: Air 4.25/6.75 after adding air. Slump 4”, Temp 72. Made three cylinders











Finished pour at around 3:30, pour went good